监理检测网论坛

注册

 

发新话题 回复该主题

抗滑桩施工方案施组 [复制链接]

1#
附件一、人员、工程量、进场材料、进场机械设备íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
1、人员:抗滑桩施工人员共30íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
2、工程量:íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
2.1开挖土石方:其中土方3175m3,石方1548 m3íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
2.2锁口、护壁C25混凝土1042 m3,桩身C30混凝土4152 m3íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
2.3钢筋427.74TíÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
3
、进场材料:32.5Mpa水泥100T,钢筋60T,碎石400 m3,砂300 m3
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
    4、进场机械设备:挖掘机2台,装载机2台,1吨电动绞车11íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
  附件二、各种材料合格证及复试报告,及混凝土配合比:íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
附件三íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

抗滑桩施工方案íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

由于大湾隧道出口位于崩坡积层中,属于不稳定地质结构,因此采取抗滑桩措施对边坡进行加固,以达到施工及隧道本身的安全。施工方案如下:íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
一、íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
施工准备íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
1.íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
1
完成洞口上截水沟施工,鉴于施工便道从隧道上方通过,且靠山一侧(向洞内方向)有排水沟,可以起到截水沟的作用,因此,不再另修截水沟。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
1.2施工放样在控制测量工作完成后,将1-6#10-19#23-28#抗滑放样出来。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
1.3试配C30C25,并确定施工配合比.íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
1.íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
4
准备开挖所需风钻,风镐及爆破器材,另每个桩配备两台手摇(或电动钻车)绞车íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
机械设备: 3m3/min5台,风镐:10台,YT18风钻:4台,手摇绞车:10台,管棚钻机:1台,锁口、护壁模板,电焊机:3台。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
1.íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
5
钢筋采购、复试与加工íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
1.íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
6
刷坡并对边坡采取喷砼、挂网、砌筑坡角墙等防护措施。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
二.施工顺序íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
21先完成隧道开挖范围以外的1-6#10-19#23-28#íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
22洞身范围仰坡开挖,再施工拱部大管棚及边墙超前小导管,浇筑洞口套拱,最后进行隧道下部开挖。开挖至H=339.28后施体,洞身范围内7-9#20-22#抗滑桩。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
三.施工方案íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
31开挖顺序íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
1-6#23-28#中心间距3m,相距搞滑桩间边距仅有1m10-19#抗滑桩中心间距为2.958m,边距仅有0.958m,因此采取隔一挖一的施工顺序。首先施工1610192328桩,计22根桩,完成后施作隧道套拱,后进行79,2022桩施工。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
32开挖方法íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
321采用人工结合风镐开挖,如遇块石则采用钻眼,小爆破,以把石头炸裂开来为目的,严禁大量装药,进入基岩采用爆破开挖。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
322桩井开挖2m后立即施作锁口,每下挖每2m下一节护壁。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
322开挖达到基岩,采取爆破后进行开挖。爆破结束,要采取一定时间排烟,或采用高压风口喷散烟尘后,施工人员再进入,进行出碴。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
33砼浇筑íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
331开挖到设计标高后,将加工好的钢筋在桩井内进行绑扎、焊接。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
332浇筑砼íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
333立模,接长地上部分(除7-9#20-22#抗滑桩)íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
四.施工注意事项íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
1.爆破作业最好采用电起爆雷管。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
2.起爆前认真清点炮孔数,起爆后要认真听取记清炮声数,如有哑炮,不要急于下桩井处理,要等待一段时间。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
3.雨天开挖采取防雨措施,可以用粘条布或其他防雨工具在桩井上方搭设防雨棚。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
4.桩井锁口高出原地15cm。防止地面水流入桩井内。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
5.桩井内可能有水,要挖积水坑,用水泵抽出排走。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

核对图纸íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

测量放样íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

施工准备íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

开挖íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

绑扎钢筋íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

浇筑íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

接长地面部分íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

准备机械íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

钢筋加工íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

砼试件íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ

íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
测量放样的注意事项:íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
大湾隧道进出口洞门墙放样计算标准,洞口墙方向为洞门所在里程沿线方向。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
因此出口抗滑桩放样,亦按洞门所在施工里程沿法线方向放样。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
仰坡放样亦相同。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
分享 转发
TOP
2#

回复:抗滑桩施工方案施组

这也叫施组呀。;PíÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
TOP
3#

回复:抗滑桩施工方案施组

bukesiyi 不可思议,这也叫施组呀íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
SZHJ
TOP
4#

回复:抗滑桩施工方案施组

这是什么呀?íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
TOP
5#

回复:抗滑桩施工方案施组

这样的施组没看见过。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
TOP
6#

回复:抗滑桩施工方案施组

呵呵,什么东西íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
辉煌路要自己去踩。
TOP
7#

回复:抗滑桩施工方案施组

这是骗人的吧íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
TOP
8#

回复:抗滑桩施工方案施组

呵呵,什么东西íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
TOP
9#

作为施工方案还是可以参考的。其实施工方案现在做的比现代小说都厚,有那个必要吗?íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
按招标文件《技术规范》要求写明就行了。íÝI¾Ô:"J\nbbs.3c3t.com‘³ÀÊèf¹ìÂ
TOP
发主话题 回复该主题